Downtimes

To properly manage downtimes it is important to highlight the differences between the possible types of downtimes. Downtimes can’t be added retroactively, and the date is always defined in UTC. If the error messages received when adding a downtime is cryptic, usually it’s due to a parsing error on the time/date.

Downtimes classification

  1. scheduled: e.g. for software/hardware upgrades, planned and agreed in advance. This needs to be announced at least 24h in advance.
  2. unscheduled: e.g. power outages, unplanned, usually triggered by an unexpected failure.

Downtimes severities

  1. WARNING: Resource will probably be working as normal, but may experience problems.
  2. OUTAGE: Resource will be completely unavailable.

WARNING, formerly known as AT_RISK, implies a type of severity that does not have operational consequences. It is only an information for users that some small temporary failures can appear. All failures during that time will be taken into account in the reliability calculations. Examples include:

  • Admins not present on site (conference, vacations).
  • Reduced redundancy in network, power or cooling.
  • Failed disk in RAID sets.

OUTAGE implies that the site/node is completely unavailable and no tickets should be created. This does not affect site metrics.

More information about downtimes can be found in the Configuration Database user documentation.

Sites in downtime

When a ticket has been raised against a site that subsequently enters in a downtime, the expiry date on the ticket can be extended.

When a ticket is opened against a site that continues to add or increase the downtime the ticket must be closed, and the NGI requested to take action either by suspending or un-certifying the site until such time that the problem is resolved. This usually happens when a middleware upgrade is due or a bug in the middleware is causing a site to fail. Sites then may choose to wait for the next middleware release rather than spend effort trying to resolve the issue locally.

Sites that are in downtime will still have monitoring switched on and therefore may appear to be failing tests. ROD must take care that when opening tickets to ensure that they don’t open tickets against sites in downtime.

If a site is in downtime for more than a month, then it is advised that the site should go to the uncertified state.

Nodes in downtime

When a node of a site is in downtime, alarms are generated but the Operations Portal distinguishes these alarms, and marks the downtime accordingly in the dashboard.

ROD should not open tickets against nodes that are in downtime.

Instructions for accounting monitoring failures

The Accounting monitoring tests are not run against the site but query the central accounting repository.

  1. If there is more than one failure for a given site, create a ticket for one of the alarms and mask all others by this one.
  2. Edit the description of the ticket to state clearly that even though the failure is reported for a given CE, this is not a CE failure but a failure on the Accounting service for the whole site.
  3. Proceed with all sites in the same way. Please beware: Accounting tests are not helped by scheduling downtime, the site admins need to get Accounting publishing working again.

Nodes not in production

When a node of a production site is declared as non-production in the Configuration Database or the node appears in BDII but is not declared in the Configuration Database, then the ROD should do the following:

  • Recommend to the sites to take these nodes out of their site BDII
  • If this is not a possibility then the site should set those nodes in downtime in the EGI Configuration Database
  • If the node is a test node and is in BDII but not in the Configuration Database, then the sites should register it and turn monitoring off.
Last modified October 4, 2022 by paolini78 : creation of the ROD pages (#509)